HEC-RAS 2D model of breach flow from the North Salem Street Dam following the stream corridor.
Project

North Salem Street Dam

Merit Group planned to remove an existing pond as part of future development in Apex, NC. RiskHydro developed a 2D HEC-RAS hydraulic model to evaluate downstream impacts from a sunny-day dam breach and support the hazard classification review. After the hazard classification was complete, we used HEC-HMS to model the watershed and establish the flows required for the planned breach channel. This work helped the owner understand NCDEQ Dam Safety requirements and coordinate pond removal with future site planning.

Location Apex, NC Client Type Private
Client Merit Group, LLC Service Area Dam Safety
Project Type Dam Removal Hydrology & Hazard Classification Support Partnership Year 2026
Project Status Complete Partners
  • Soil & Environmental Consultants

Key Project Highlights

The planned pond removal needs to meet applicable NCDEQ Dam Safety requirements. The hazard classification review informs the flows the permanent breach channel must convey. The project also involves a complex downstream crossing, with a culvert that has multiple bends and connects to stormwater structures. The owner needed the analysis to account for those conditions while coordinating dam removal with future site planning.

Project Features

  • Planned pond removal for private development
  • Sunny day dam breach analysis
  • 2D HEC-RAS model with pipe network features
  • Hazard classification review support
  • HEC-HMS watershed modeling
  • North Carolina PMP Study precipitation data
  • Inflow hydrographs for reach channel design
  • Review of preliminary site drainage plans

Looking Ahead

The hydrologic and hydraulic modeling gives the project team information to evaluate the planned breach channel and understand how flows move through the downstream crossing. If final grading or drainage plans route additional runoff to the channel, the analysis can be revisited as part of the removal process.

RiskHydro helps dam owners understand regulatory requirements and fit dam removal into future site planning. If you are considering removing or modifying a pond dam, contact RiskHydro to discuss the dam safety review process and hydrologic and hydraulic modeling support.