Lupo Lake Dam
Raeford, NC
RiskHydro evaluated an existing, unclassified dam within the proposed Cedar Creek community in Creedmoor, NC for Gander Development, LLC. RiskHydro modeled sunny day and spillway design flood breach scenarios, compared breach and non-breach flood conditions to isolate the incremental consequence of dam failure, and used the results to support a Jurisdictional Determination and Hazard Classification (JDHC) request to the NCDEQ Dam Safety Program. The analysis supported an intermediate hazard (Class B) classification, and because the dam falls under the size thresholds in the Dam Safety Law of 1967, that classification made it exempt from state dam safety regulation. The recommendation was approved on the initial submittal.
| Location Creedmoor, NC | Client Type Private |
| Client Gander Development, LLC Mary Lane Holdings, LLC (Owner) | Service Area Dam Safety |
| Project Type Dam Breach Analysis & Hazard Classification | Partnership Year 2026 |
| Project Status Complete |
Partners
|
The dam sits within Gander Development’s proposed Cedar Creek community. It predates current dam safety regulation and did not appear in the NCDEQ Dam Safety Program inventory, so its jurisdictional status was an open question rather than a matter of record. Gander Development needed to know whether the dam would trigger state regulation before finalizing the community’s layout and road network.
Gander Development wanted to keep the pond as a community amenity, with a greenway around it that would let residents connect with nature. Before committing to that plan, they needed to understand the actual risk the dam posed and what long-term regulatory compliance would cost if the dam were classified as jurisdictional.
Two roadway crossings are also proposed downstream of the dam. Gander Development needed to understand how breach flooding would interact with those crossings before committing to the road network, so that the layout reflected the dam’s actual failure consequences rather than an assumption about them.
RiskHydro approached the dam as a flood risk problem, not just a desktop classification exercise. We built hydrologic models in HEC-HMS to generate reservoir inflow for the governing spillway design flood, then used two-dimensional HEC-RAS modeling to route both breach and non-breach flows downstream and compare the results side by side. Running that comparison across sunny day and hydrologic loading conditions gave Gander Development a defensible basis for hazard classification and a clear picture of how breach flooding would interact with the community’s proposed road crossings. Key tasks included:
NCDEQ Dam Safety approved the recommended classification and exempt determination on the initial JDHC submittal, with no additional review cycles required. Gander Development moved forward with the Cedar Creek community knowing the dam’s actual flood risk, not an assumed one, and with both existing and proposed conditions evaluated rather than assumed.
Exemption under the Dam Safety Law of 1967 is not a property of the dam alone. A dam that falls under the size thresholds is exempt only if it is not high hazard, so the exempt determination rests on the classification, and the classification rests on what is downstream. The determination here reflects the dam and the downstream conditions as they exist today. RiskHydro also evaluated the community as proposed, so Gander Development has that picture in hand while the layout can still change, which is when it is most useful.
That distinction is at the center of where North Carolina’s dam safety rules are heading. The proposed revisions to 15A NCAC 02K, open for public comment through October 16, 2026, would explicitly require that planned future downstream development be considered in hazard classification, would tie road-related consequences to measured traffic volumes rather than road type, and would formally establish incremental damage analysis as a tool for classification and reclassification. A dam that is exempt under current conditions is not necessarily exempt under future ones.
If you own a dam, or you are evaluating land with one on it, contact RiskHydro to discuss what the proposed changes mean for your classification.
“RiskHydro turned a potentially complicated dam safety issue into a clear and manageable path forward. Their analysis was thorough, practical, and approved by NCDEQ without revisions, allowing our team to continue planning with confidence.” – Jonathan Parsons, PLA, NC-GC, Director of Community Planning, Gander Development, LLC