ballentine-farms-pond-dam
Project

Ballentine Farms Pond Dam

Ballentine Farms Pond Dam is a High Hazard dam in Fuquay-Varina, North Carolina, regulated by the NCDEQ Dam Safety Program. The dam owner elected to decommission the structure by constructing a permanent breach channel, which will allow storm flows to pass through the embankment without re-impounding the former reservoir. To support breach channel design, RiskHydro performed a hydrologic analysis to develop Inflow Design Floods for the contributing watershed. The analysis was conducted for both existing and future land use conditions to account for anticipated development, and produced the peak design flows needed to size the breach channel and determine the extent of required channel armoring in accordance with NCDEQ Dam Safety Program requirements.

Location Fuquay-Varina, NC Client Type A/E Partner
Client Soil & Environmental Consultants, Inc. Service Area Dam Safety
Project Type Dam Removal Partnership Year 2026
Project Status In Review

Key Project Highlights

NCDEQ Dam Safety Program requirements set specific design standards for permanent breach channels on High Hazard dams. The channel has to pass the 1/3 PMP storm event without re-impounding the former reservoir, and it has to be lined or stabilized up to the water surface elevation associated with the 100-year peak flow. Meeting those thresholds requires defensible peak inflow values developed in accordance with current NCDEQ hydrologic guidance.

The watershed sits in a fast-growing part of Wake County, and the Town of Fuquay-Varina’s 2040 land use plan shows significant development planned within the drainage area. Designing for existing conditions alone could leave the channel undersized within a few years of construction. The analysis needed to account for both where the watershed is today and where it is headed.

Project Features

  • Hydrologic modeling (HEC-HMS) for existing and future land use conditions

  • Future land use translated from municipal planning categories to TR-55 curve numbers

  • Peak design flows established for five storm events from 10-year through 1/3 PMP

  • 2025 NC PMP Study precipitation inputs

  • Technical basis established for both breach channel sizing and channel armoring extent

  • Analysis completed in accordance with NCDEQ Dam Safety Program hydrologic design guidance

“RiskHydro’s experience and expertise in hydrologic and hydraulic modeling, and thorough understanding of NCDEQ Dam Safety regulatory requirements has proven invaluable on multiple dam related projects.” Patrick Smith, PE, LEED-AP, President, Soil & Environmental Consultants, Inc.